At the May 5 borough council meeting, a resident asked a simple question: when would the new trail bridge go in? According to the meeting minutes, Council President Jamie Murphy said construction was aimed to start before September 15, "but the bulk of the work will be done in 2027."
Four months later, the same question came up again at the September 8 meeting. The September 8 minutes record Murphy saying prep work would start by the end of the following week. She said no work would occur after September 15 until after March 15, 2027, because of limits tied to Peapack Brook's status as a Class I trout stream. The borough's newest walking link, a footbridge meant to carry people between downtown and Natirar, runs on the brook trout's calendar.
The brook decides when the work happens
The state lists Peapack Brook in its surface water standards as "PEAPACK BROOK (Gladstone) - Entire length FW2-TP(C1)." That puts the whole stream in the trout-production class, with Category One protection. Trout-production waters are where trout reproduce. A December 2005 state Fish & Wildlife trout water report marked Peapack Brook as having reproducing brook trout. That's the most recent species-level record in the material here.
The work limits come from New Jersey's freshwater wetlands rules.
The borough scheduled the bridge work around the limits. The $8,050 site-work contract went to Jerry Conover Excavating, Inc. at the September 8 meeting, a week before September 15. By the borough's own schedule, the next phase begins after March 15.
What the pause is holding up
The bridge is more than a stream crossing. At the May 5 meeting, Murphy described it as a section of trail that lets residents walk safely to Natirar, and from Natirar into town. She and Environmental Commission Chair Kappler had asked the county's open space program for bridge funding, and the county awarded the borough $410,000. The minutes also tie the bridge to a larger plan: a trail network meant to keep newer developments in the borough from feeling isolated from other parts of town.
The money comes through Somerset County's Trails Grant Program. It's paid for by the county's Open Space Preservation Trust Fund and can cover trail design, construction, and related facilities. The borough handles the engineering. Resolution 87-26 hired Boswell Inc. to design one abutment and one pier for "a prefabricated pedestrian bridge over Peapack Brook," for up to $24,000. The money comes from a borough account labeled "TRAILS."
The same May 5 meeting dealt with the land on either side. The council approved a trail easement agreement with 158 Route 206 PG, LLC. It also approved assigning part of the developer's agreement for 100 Route 206 PG, LLC to Pulte Homes of NJ. When another resident asked where the trail would actually run, Murphy said there would be a pedestrian section of the gate leading onto the trails and an easement with the house beside that gate. The trail won't enter Natirar directly. It will run about 20 feet south of it.
One small issue has already appeared near the trailhead. In May, the council discussed drivers using the parking area by the trails to turn around, and the borough started with signs. By September, a resident reported that the signs had been up for two months without solving it, especially in the evening, and suggested a fence or bushes. Murphy said she'd take that up with the head of the Department of Public Works.
Anglers know the brook's other calendar
The trout that set the bridge schedule share the brook with a spring fishing season. The state's 2026 freshwater fishing digest lists Peapack Brook as a stocked water, five miles along its entire length. In spring 2026, according to the state's allocation sheet, the brook received 510 trout before the season opened. After that came 200 trout each Wednesday on April 22, April 29, May 6, and May 13, and 130 on May 20.
Fall is a different story. The 2026 fall stocking schedule doesn't include Peapack Brook. The nearest fall stocking was the North Branch of the Raritan River, which got 1,280 trout on Tuesday, October 13. The North Branch's stocked stretch starts below Ravine Lake Dam in Natirar County Park, the same park the new trail is meant to reach. On Peapack Brook itself, the state lists St. Brigid's Parish Center as an access point, reached by Route 206, Pottersville Road, and Main Street. The state hadn't posted a spring 2027 schedule as of late October.
Two Peapack Brook crossings on the March 2027 calendar
The Brook Street bridge isn't the only project over Peapack Brook water scheduled for spring. Somerset County plans to replace County Bridge No. D1303, which carries Mendham Road over a tributary to Peapack Brook between Dewey and Jackson Avenues. The county lists the current structure as being in serious condition. It cites section loss on the bottom of the steel pipe, voids in the headwall, and undermining of more than four feet at the outlet. The replacement is a concrete elliptical pipe with a precast concrete headwall, plus resurfacing and a new manhole. The project is county-funded, and the county planned to advertise it for bids this month.
Here's how the two projects line up for spring:
| Project | Who runs it | When work happens | What changes for residents |
|---|---|---|---|
| Brook Street pedestrian bridge over Peapack Brook | Borough, with a $410,000 county trails grant | Borough planned no work from September 15, 2026 until after March 15, 2027; bulk of the work in 2027 | A walking link between town and the Natirar area |
| Mendham Road Bridge D1303 over a Peapack Brook tributary | Somerset County | Starting March 2027, about two months | Bridge closed to cars and pedestrians; detour via Jackson Avenue, Main Street (County Route 671), and Dewey Avenue; driveway access maintained |
The county held a virtual public information meeting on the Mendham Road project on September 30. Its display boards, including the detour plan, are posted on the project page. For anyone who drives Mendham Road toward Main Street, those two months next spring will mean the Jackson-to-Dewey detour every trip.
What's moving before spring
Some of the borough's road work doesn't depend on the brook, and a new ordinance changes how residents will hear about it.
- Riverview Avenue. As of the September 8 meeting, the county's Pottersville Road bridge work was done, but Riverview Avenue stayed closed because the custom guardrails didn't fit and had to be remade. The county had offered the option of reopening the avenue but hadn't given a timeline.
- Resurfacing and crosswalk. The same meeting awarded the borough's improvement and resurfacing project to Riverview Paving, Inc. It also gave Jerry Conover Excavating a $36,713 contract for Main Street crosswalk improvements at the Liberty Park entrance.
- Future streets. The October 13 agenda included resolutions to prepare plans and bid documents for Apgar Avenue and Bodine Avenue. That's the planning stage, before any construction.
- Work notices. Ordinance 1173-2026 was adopted October 13. It sets notice, scheduling, publication, cleanup, and property-restoration requirements for non-emergency work in borough rights-of-way.
- Alerts. In May, Mayor Corigliano called PG Notify the best way to follow the bridge or any other borough project. In September, the borough announced its new Everbridge alert system. It's opt-in and covers road closures and community updates.
On the calendars the borough and county have published, the Brook Street bridge work resumes after March 15, 2027, and the Mendham Road closure starts that same month and runs about two months.